February 2014 Trailbuild planning

I had a recce in the BH this morning and marked out the work area roughly. From the photos it looks like it needs more sweep in the bend to steer you away from the tree more, rather than cutting the line as I thought.
I hadn’t realised how bad it was down there as I normally don’t go in there when it’s wet . I think we may need 2 trailer loads. The good news is there there’s not too much to dig out at the bottom of the slope as the tyres have dug down about the right amount……………..it just needs squaring off and tidying.
I also checked the pile at Rendlesham, and there’s enough left for Sunday but not much more. I think it’s time to get a couple of loads delivered to Tunstall as we did for the drainage stone. I will find out from the FC what we are allowed to import to the forest and get it priced-up.
If we get a good enough turn-out, we could add a short spur into the work to take the other entry point in(RH side in pictures).
Archives
- July 2023
- June 2023
- April 2023
- January 2023
- November 2022
- May 2022
- March 2022
- December 2021
- October 2021
- July 2021
- May 2021
- February 2021
- January 2021
- November 2020
- October 2020
- May 2020
- February 2020
- January 2020
- December 2019
- November 2019
- October 2019
- June 2019
- May 2019
- February 2019
- January 2019
- December 2018
- November 2018
- March 2015
- August 2014
- May 2014
- March 2014
- February 2014
- January 2014
- July 2013
- December 2012
- July 2012
- June 2012
- April 2012
- February 2012
- January 2012
- November 2011
- October 2011
- August 2011
- July 2011
- June 2011
- April 2011
- March 2011
- February 2011
- January 2011
- December 2010
- November 2010
- October 2010
- September 2010
- August 2010
- July 2010
- June 2010
- May 2010
- April 2010
- March 2010